Vendor Name: Exin
Exam code: PR2F
Exam Name: PRINCE2® Foundation
Click the link below to get full version
http://www.examcertify.co.uk/PR2F.html
Question: 1
|
Identify the
missing word(s) from the following sentence. A project is a temporary
organization that is created for the purpose of delivering one or more business
products according to an agreed?
A. Senior User
B. Business Case
C. Change
D. Cost
Answer: B
|
Question: 2
|
According to
PRINCE2, which of the following is a characteristic of a project compared to
that of business operations?
A. Incurs cost
B. Introduces
business change
C. Delivers
benefits
D. Creates products
Answer: B
|
Question: 3
|
Which of the
following is FALSE?
A. Manage risks is
a PRINCE2 principle
B. Manage by
exception is a PRINCE2 principle
C. Focus on
products is a PRINCE2 principle
D. Tailor to suit
the project environment is a PRINCE2 principle
Answer: A
|
Question: 4
|
According to
PRINCE2, which of the following are the aspects of project performance to be
managed?
A. Processes,
themes, principles
B. Time, cost,
quality, people
C. Time, cost,
quality
D. Time, cost,
quality, scope, benefits, risk
Answer: D
|
Question: 5
|
What environment
does PRINCE2 assume?
A. Third party
B.
Customer/Supplier
C. Fixed-price
contract
D. Management and
Specialist
Answer: B
|
Question: 6
|
A characteristic of
a project is that they come with an element of uncertainty. Which of the
following PRINCE2 themes will help with the identification and management of
such uncertainty?
A. Quality
B. Risk
C. Change
D. Organization
Answer: B
|
Question: 7
|
Which is a benefit
of using PRINCE2?
A. Stakeholders are
kept out of planning and decision making
B. Participants
understand each other's roles and needs
C. Stakeholders are
not involved in assuring the project work
D. All problems are
escalated to all stakeholders
Answer: A
|
Question: 8
|
If an informal
issue is defined as a problem or concern, where should it first be recorded?
A. Issue Register
B. Risk Register
C. Daily Log
D. Exception Report
Answer: C
|
Question: 9
|
Which of the
following statements about the Project Initiation Documentation are true?
1. The Project
Initiation Documentation is used to ensure that a sound basis exists.
2. The Project
Initiation Documentation should be updated at the end of each stage to reflect
the current status of a project before the Project Board authorizes a project,
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are
true
D. Neither 1 or 2
are true
Answer: C
|
Question: 10
|
Which is the
purpose of the Change theme?
A. Prevent change
to baselined products
B. Identify, assess
and control any potential and approved changes to baselined products
C. Establish
mechanisms to monitor and compare actual achievements against those planned
D. Assess and
control uncertainty
Answer: B
|
Question: 11
|
Why is a Project
Brief produced?
A. To act as a
trigger for the Starting up a Project process
B. To record the
strategies and management controls to be used by a project
C. To provide a
full and firm foundation for the initiation of a project
D. To be used by
the Project Board as a basis for reviewing the progress of a project
Answer: C
|
Question: 12
|
Identify the
missing words in the following sentence. An objective of the Closing a Project
process is to ensure that provision has been made to address [?] through
follow-on action recommendations.
A. the measurement
of benefits NOT yet realized
B. the handover of
products
C. open issues and
risks
D. the release of
resources
Answer:
C
|
Question: 13
|
In what process is the authorization to deliver the
project's products given?
A. Starting up a
Project
B. Initiating a
Project
C. Managing a Stage
Boundary
D. Directing a
Project
Answer: D
|
Question: 14
|
Which of the
following is NOT part of quality planning?
A. Define quality
responsibilities
B. Gain acceptance
of the project product
C. Agree acceptance
criteria
D. Set quality
tolerances
Answer: B
|
Question: 15
|
Which should be
provided by a project mandate?
A. Terms of
reference
B. Detailed
Business Case
C. Stage tolerances
D. Initiation Stage
Plan
Answer: A
|